McLoughlin Elementary

McLoughlin Elementary

Built in 1975

About the Project

Safety and Security

  • Secure perimeter fencing around play areas
  • Reconfiguration of parent drop-off/pick-up areas and parking to ensure adequate driving aisle widths and safe pedestrian routes to entries
  • New accessible parking
  • New interior door to create secure vestibule
  • Internal relocation and reconfiguration of main office including new vision glazing at the reception to achieve appropriate supervision and surveillance of main entry
  • Office areas will be upgraded with new finishes and furniture
  • Ornamental fencing at exterior breezeway to provide secure pathways to all classrooms
  • Various site grading and drainage issues
  • Access control and security infrastructure upgrades
Project Updates
bc_el

Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com

Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us

Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us

Stephen Wasserbeger
Day CPM
Bond Manager for Safety & Security, CTE, and District Upgrades
stephen.wasserberger@orecity.k12.or.us

Schedule

2020 2021
J F M A M J J A S O N D J F M A M J J A S O N D
Design
Construction
Closeout
  • Pre-Design: July. – October, 2020
  • Design: November 2020 – February, 2021
  • Land Use: March – June, 2021
  • Bid-Award: September – December, 2020
  • Construction: June – September, 2021
  • Closeout: September – November, 2021