McLoughlin Elementary
Built in 1975

Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com
Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us
Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us
Stephen Wasserbeger
Day CPM
Bond Manager for Safety & Security, CTE, and District Upgrades
stephen.wasserberger@orecity.k12.or.us
Schedule
- Pre-Design: July. – October, 2020
- Design: November 2020 – February, 2021
- Land Use: March – June, 2021
- Bid-Award: September – December, 2020
- Construction: June – September, 2021
- Closeout: September – November, 2021