Redland Elementary

Redland Elementary

Built in 1948

About the Project

Security Updates

  • Secure perimeter fencing around play areas
  • Relocate and consolidate soft and hard surface play areas around existing covered play to increase supervision
  • New secure vestibule and main office area under existing covered play roof
  • Various site grading and drainage issues
  • Relocate soft play to facilitate adequate supervision
  • Access control and security infrastructure upgrades


Redland Construction on CTE Space 8/7/2020 from Oregon City School District on Vimeo.

Project Updates

March 2021:

Safety and security improvements continue with the construction and Redland Elementary. The new entrance vestibule has been installed, which will allow the front office the ability to monitor all of the guests and visitors to the building. The playground has been largely completed, as has the landscaping around the entrance of the building.

February 2021:

bc_el

Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com

Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us

Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us

Stephen Wasserbeger
Day CPM
Bond Manager for Safety & Security, CTE, and District Upgrades
stephen.wasserberger@orecity.k12.or.us

Schedule

2020 2021
J F M A M J J A S O N D J F M A M J J A S O N D
Design
Construction
Closeout
  • Pre-Design: January – February, 2020
  • Design: March – April, 2020
  • Land Use: May – July, 2020
  • Bid-Award: February – April, 2020
  • Construction: May – December, 2020
  • Closeout: January – February, 2021