Safety and Security

  • New interior doors to create secure vestibule

  • Internal reconfiguration of main office including new vision glazing at the reception to achieve appropriate supervision and surveillance of new vestibule and main entry

  • Access control and security infrastructure upgrades

Schedule

  • Pre-Design: July – October, 2020

  • Design: November 2020 – February, 2021

  • Land Use: March – June, 2021

  • Bid-Award: September – December, 2020

  • Construction: June – September, 2021