Built 1969
Candy Lane elementary SChool
Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com
Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us
Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us
Stephen Wasserbeger
Day CPM
Bond Manager for Safety & Security, CTE, and District Upgrades
stephen.wasserberger@orecity.k12.or.us
Safety and Security
New secure vestible
Renovated office area and student health room, staff work room, and staff room
Expanded security video
Upgraded technology infrastructure
New intercom
New emergency radios
New interior door locks
Improved ADA access
Additional secure fencing
Schedule
Pre-Design: January – February, 2020
Design: March – April, 2020
Land Use: May – June, 2020
Bid-Award: February – April, 2020
Construction: May, 2020 – January, 2021
Closeout: January – February, 2021