Candy Lane Elementary

Candy Lane Elementary

Built in 1969

About the Project

Safety and Security

  • Secure perimeter fencing around play areas
  • Reconfiguration of parent drop-off/pick-up areas and parking to ensure adequate driving aisle widths and safe pedestrian routes to entries
  • New accessible parking
  • New interior door to create secure vestibule
  • Internal relocation and reconfiguration of main office including new vision glazing at the reception to achieve appropriate supervision and surveillance of main entry
  • Office areas will be upgraded with new finishes and furniture
  • Upgrading ADA access and accommodations
  • Ornamental fencing at exterior breezeway to provide secure pathways to all classrooms
  • Various site grading and drainage issues
  • Access control and security infrastructure upgrades
Project Updates

March 2021 update:

Construction is complete on the perimeter fencing, and the parking lot redesign for pedestrian safety and new accessible parking spots are also complete. The office improvements are also complete, and safety and security upgrades are finished throughout the building.

February 2021 update:

Here's the latest collection of photos from construction progress at Candy Lane Elementary

bc_el

Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com

Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us

Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us

Stephen Wasserbeger
Day CPM
Bond Manager for Safety & Security, CTE, and District Upgrades
stephen.wasserberger@orecity.k12.or.us

Schedule

2020 2021
J F M A M J J A S O N D J F M A M J J A S O N D
Design
Construction
Closeout
  • Pre-Design: January – February, 2020
  • Design: March – April, 2020
  • Land Use: May – June, 2020
  • Bid-Award: February – April, 2020
  • Construction: May, 2020 – January, 2021
  • Closeout: January – February, 2021