Eastham Community Center

Eastham Community Center

About the Project

Eastham Community Center Entrance

Safety and Security

  • Secure perimeter fencing around play areas
  • Speed bumps and crosswalks for traffic control and safe pedestrian routes to main entry and play areas
  • New interior door to create secure vestibule
  • Internal relocation and reconfiguration of main office including new vision glazing at the reception to achieve appropriate supervision and surveillance of main entry
  • New corridor at lower level for accessible connection to bus drop-off/pick-up area
  • Additional parking
  • Access control and security infrastructure upgrades
Project Updates

     

bc_el

Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com

Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us

Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us

Schedule

2020 2021
J F M A M J J A S O N D J F M A M J J A S O N D
Design
Construction
Closeout
  • Pre-Design: January – February, 2020
  • Design: March – April, 2020
  • Land Use: May – June, 2020
  • Bid-Award: February – April, 2020
  • Construction: May, 2020 – January, 2021
  • Closeout: January – February, 2021