The Gardiner Middle School community will be getting an entire new middle school in time for the 2021-2022 school year. This is an excited opportunity for students, staff, parents and community to shape the future of their neighborhood school for years to come.

The building says: “We are a Place of Learning”

  • Warm, Welcoming, and Safe environment

  • Student-focused

  • A Place for our Community & Families

  • Supports active, Multi-modal Learning

  • Relevant Innovative Technology

  • Flexible for Future Learning Modalities

  • Collaborative Opportunities at All Levels

  • Strong Connection to the Outdoors

  • Transparency

  • Daylighting

Schedule

Planning and Design: November 2018 - March 2020

Construction: March 2020 - December 2021

  • Phase 1 New Building Construction Start (23 MARCH 2020)

  • Phase 1 Early Access (26 JULY 2021)

  • Phase 1 New Building Substantial Completion (31 JULY 2021)

  • Phase 1 Final Completion (7 SEP 2021)

  • Phase 2 Abatement/Demolition of Existing Gardiner Middle School (14 JUNE 2021 - 2 AUG 2021)

  • Phase 3 Fields (4 AUG 2021 – 31 DEC 2021)

Project Completion: January 2022