Pre 2018 Bond - Built 1954 | Post 2018 Bond - Built 2020
Gardiner Middle SChool
Tracy Goodman
Day CPM
Project Manager for Gardiner
goodman@orecity.k12.or.us
Michael Sweeten
Principal
michael.sweeten@orecity.k12.or.us
David A Johnson
BRIC Architecture, Inc.
Lead Architect
david.johnson@bric-arch.com
The Gardiner Middle School community will be getting an entire new middle school in time for the 2021-2022 school year. This is an excited opportunity for students, staff, parents and community to shape the future of their neighborhood school for years to come.
The building says: “We are a Place of Learning”
Warm, Welcoming, and Safe environment
Student-focused
A Place for our Community & Families
Supports active, Multi-modal Learning
Relevant Innovative Technology
Flexible for Future Learning Modalities
Collaborative Opportunities at All Levels
Strong Connection to the Outdoors
Transparency
Daylighting
Schedule
Planning and Design: November 2018 - March 2020
Construction: March 2020 - December 2021
Phase 1 New Building Construction Start (23 MARCH 2020)
Phase 1 Early Access (26 JULY 2021)
Phase 1 New Building Substantial Completion (31 JULY 2021)
Phase 1 Final Completion (7 SEP 2021)
Phase 2 Abatement/Demolition of Existing Gardiner Middle School (14 JUNE 2021 - 2 AUG 2021)
Phase 3 Fields (4 AUG 2021 – 31 DEC 2021)
Project Completion: January 2022