Gardiner Middle School

Gardiner Middle School

Built in 1954

About the Project

The Gardiner Middle School community will be getting an entire new middle school in time for the 2021-2022 school year. This is an excited opportunity for students, staff, parents and community to shape the future of their neighborhood school for years to come.

The building says: “We are a Place of Learning”

  • Warm, Welcoming, and Safe environment
  • Student-focused
  • A Place for our Community & Families
  • Supports active, Multi-modal Learning
  • Relevant Innovative Technology
  • Flexible for Future Learning Modalities
  • Collaborative Opportunities at All Levels
  • Strong Connection to the Outdoors
  • Transparency
  • Daylighting
Project Updates

July 2021

Last month, the main entrance flatwork was poured, and all exterior elevations were worked on. The generator was set and installed, and landscaping and irrigation installation took place throughout the month. Bleacher seats were poured in the Learning Neighborhoods. Gym equipment and flooring arrived and were installed. Solar panel racking installation is currently ongoing on the Timber Hall roof.

You can read the full status report here.

June 2021

With students officially out of the building for the summer, construction crews have begun their demolition of the old Gardiner building.

May 2021

Work continued on all elevations of the building’s exterior. Exterior storefronts arrived for the first time and installation began on the West side. Metal wall panel framing and entry soffit panels were installed at the West elevation as well. Work also continued in the Learning Neighborhoods with MEP rough-ins, cover inspections, framing & high rock and steel work on the stairs. Interior framing in the gym was completed and gypsum board begin installing. Soffit Framing in Timber Hall made significant progress.

The front entrance storefronts were also installed and the framing for the entry corridor metal wall panels began installation. Guardrails were installed in many of the stairways. In the gym, drywall paint began. The roofing top cap in Sector A was completely finished and material was stoked for the covered play area to begin. Another important milestone was beginning to secure the building – access is now restricted to ensure the building is safe.

July 2020 Update

Proposed Exterior

This is tab content. Click to edit this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Proposed Interior

This is tab content. Click to edit this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

bc_el

Tracy Goodman
Day CPM
Project Manager for Gardiner
goodman@orecity.k12.or.us

Michael Sweeten
Principal
michael.sweeten@orecity.k12.or.us

David A Johnson
BRIC Architecture, Inc.
Lead Architect
david.johnson@bric-arch.com

Live Camera

Schedule

2019 2020 2021 2022
J F M A M J J A S O N DJ F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Design
Construction
Closeout

Planning and Design: November 2018 - March 2020

Construction: March 2020 - December 2021

  • Phase 1 New Building Construction Start (23 MARCH 2020)
  • Phase 1 Early Access (26 JULY 2021)
  • Phase 1 New Building Substantial Completion (31 JULY 2021)
  • Phase 1 Final Completion (7 SEP 2021)
  • Phase 2 Abatement/Demolition of Existing Gardiner Middle School (14 JUNE 2021 - 2 AUG 2021)
  • Phase 3 Fields (4 AUG 2021 – 31 DEC 2021)

Project Completion: January 2022