Built 1966
HOlcomb Elementary SChool
Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com
Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us
Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us
Stephen Wasserbeger
Day CPM
Bond Manager for Safety & Security, CTE, and District Upgrades
stephen.wasserberger@orecity.k12.or.us
Safety and Security
New secure vestibule
New office area and student health room
Expanded security video
Upgraded technology infrastructure
New intercom
New emergency radios
New interior door locks
Additional adult bathrooms
Renovated staff room
New main hallway LED lighting
New paint
Additional secure fencing
Improved ADA access
Schedule
Pre-Design: January – February, 2020
Design: March – April, 2020
Land Use: May – June, 2020
Bid-Award: February – April, 2020
Construction: May, 2020 – January, 2021
Closeout: January – February, 2021