Built 1975

John Mcloughlin Elementary SChool

Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com

Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us

Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us

Stephen Wasserbeger
Day CPM
Bond Manager for Safety & Security, CTE, and District Upgrades
stephen.wasserberger@orecity.k12.or.us

Safety and Security

  • New secure vestibule

  • Renovated office area and student health room

  • Improved bus entrance to school

  • Expanded security video

  • Upgraded technology infrastructure

  • New intercom

  • New emergency radios

  • New interior door locks

  • Improved ADA access

  • Additional secure fencing

Schedule

  • Pre-Design:  July. – October, 2020

  • Design:  November 2020 – February, 2021

  • Land Use:  March – June, 2021

  • Bid-Award:  September – December, 2020

  • Construction:  June – September, 2021

  • Closeout:  September – November, 2021