Built 2003

Oregon City High SChool

Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com

Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us

Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us

Stephen Wasserbeger
Day CPM
Bond Manager for Safety & Security, CTE, and District Upgrades
stephen.wasserberger@orecity.k12.or.us

Safety & Security Upgrades 

  • Construct new secure vestibule in existing lobby

  • Install bollards at main entrance

  • Improved technology infrastructure

  • Landscape improvements

  • Additional secure fencing

  • Upgraded window glazing

CTE Upgrades

  • Renovate/expand Culinary Lab

  • Create Health Sciences Lab

  • Relocate/Renovate Career/College Center

  • New signage

Schedule

  • Pre-Design: January – February 2020

  • Design: March – April 2020

  • Land-Use: May – July 2021

  • Bid Award: February – April 2021

  • Construction: May 2020 – February 2021

  • Closeout: February – March 2021