Built 2003

Oregon City High SChool

Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com

Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us

Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us

Stephen Wasserbeger
Day CPM
Bond Manager for Safety & Security, CTE, and District Upgrades
stephen.wasserberger@orecity.k12.or.us

OCHS - Safety & Security Upgrades 
(Summer 2020 work - now complete)

Project Summary:

  • New Safety Bollards installed at the main High School entry as a protective physical barrier.

  • New School Guard glass installed at reception area windows.

  • New reception entry doors with School Guard glass.

  • Strobe Light Fixtures installed (interior and exterior)  

  • Interior courtyard site drainage repairs to address run-off water intrusion in the building.

Schedule

  • Pre-Design: January – February 2020

  • Design: March – April 2020

  • Land-Use: May – July 2021

  • Bid Award: February – April 2021

  • Construction: May 2020 – February 2021

  • Closeout: February – March 2021