Oregon City Service Learning Academy
Joshua Dodson
Day CPM
Project Executive
jdodson@daycpm.com
Angela Khosa-Marangwanda
Day CPM
Project Coordinator for Support Services
angela.khosa-marangw@orecity.k12.or.us
Wes Rogers
Oregon City School District
Bond Manager
wes.rogers@orecity.k12.or.us
Stephen Wasserbeger
Day CPM
Bond Manager for Safety & Security, CTE, and District Upgrades
stephen.wasserberger@orecity.k12.or.us
Safety and Security
Secure perimeter fencing around Early Childhood entrance and play areas and at school garden
Extend roof overhang at Early Childhood entrance New sidewalk outside of secure fencing around school garden
New storage shed
New interior door to create secure vestibule
Internal relocation and reconfiguration of main office including new vision glazing at the reception to achieve appropriate supervision and surveillance of main entry
New double doors at cafeteria to provide pathway from Early Childhood program areas to shared gymnasium
New corridor double doors to separate program areas
Access control and security infrastructure upgrade
Schedule
Pre-Design: July. – October, 2020
Design: November 2020 – February, 2021
Land Use: March – June, 2021
Bid-Award: September – December, 2020
Construction: June – September, 2021
Closeout: September – November, 2021