Pre 2018 Bond - Built 1965 | Post 2018 Bond - Built 2021

Tumwata (ogden) Middle SChool

Ben Kates
Principal, Tumwata Middle School
benjamin.kates@orecity.k12.or.us

David A Johnson
Lead Architect
BRIC Architecture
david.johnson@bric-arch.com

Toni Esteban
Associate Architect
BRIC Architecture
tonie.esteban@bric-arch.com

The Tumwata (Ogden) Middle School community will be getting an entirely upgraded and updated middle school in time for the 2021/2022 school year. This is an excited opportunity for students, staff, parents and community to shape the future of their neighborhood school for years to come.

The building says: “We are a Place of Learning”

  • Warm, Welcoming, and Safe environment

  • Student-focused

  • A Place for our Community & Families

  • Supports active, Multi-modal Learning

  • Relevant Innovative Technology

  • Flexible for Future Learning Modalities

  • Collaborative Opportunities at All Levels

  • Strong Connection to the Outdoors

  • Transparency

  • Daylighting

Schedule

Planning and Design: November 2018 - March 2020

Construction: March 2020 - December 2021

  • Phase 1 & 2  Areas of building Start (MARCH 2020)

  • Phase 1 Areas of Building Final Completion (MAY 2021)

  • Phase 2 Areas of Building Final Completion (SEP 2021)

  • Phase 3 Renovation of existing Athletic Fields (JUNE 2021 – OCT 2021)

Project Completion: January 2022